STANDARD LISTINGS ▲ CONTRACT
|
STATUS
|
|
COMMUNITY INFORMATION ▲ CONTRACT
|
OPENS
|
FULL SCOPE CLOSES
|
PARTIAL SCOPE CLOSES
|
DOCS
|
FULL SCOPE EOI
|
PARTIAL SCOPE EOI
|
| | External Access Road and Bus Stop | 17 Apr 2020 | 01 May 2020 | |
| | |
| Future Generation is seeking to identify suppliers that have the ability and plant equipment to provide:
. External Access Road & Bus Stop to the Polo Flat Segment Factory.
. Fully operational plants with monitoring systems and accessories.
. Equipment should be to Industry safety and maintenance standards. |
STATUS
|
|
COOMA SEGMENT FACTORY ▲ CONTRACT
|
OPENS
|
FULL SCOPE CLOSES
|
PARTIAL SCOPE CLOSES
|
DOCS
|
FULL SCOPE EOI
|
PARTIAL SCOPE EOI
|
| | Concrete FRP Footings and Slabs and Aggregate Bays | 17 Apr 2020 | 01 May 2020 | |
| | |
| Future Generation is seeking to identify suppliers that have the ability and plant equipment to provide:
. Concrete FRP Footings, Slabs, Aggregate Bays at the Polo Flat Segment Factory |
STATUS
|
|
MISCELLANEOUS ▲ CONTRACT
|
OPENS
|
FULL SCOPE CLOSES
|
PARTIAL SCOPE CLOSES
|
DOCS
|
FULL SCOPE EOI
|
PARTIAL SCOPE EOI
|
| | CT01 and Upper Chamber Excavation Drill and Blast | 21 Jan 2021 | 04 Feb 2021 | |
| | |
| This scope of works covers the excavation of the upper chamber of the downstream surge shaft (DSS), including the construction access tunnel CT01. |
| | Running of Precast Factory | 21 Jan 2021 | 04 Feb 2021 | |
| | |
| Scope of Work encompasses the Implementation of a proper Organization (manpower along with Technical, Quality and HSE Supervision) to carry out the Lining Segments' production throughout the production cycle.
. |
| | Cross Passages Excavation Works | 21 Jan 2021 | 18 Feb 2021 | |
| | |
| This scope of works covers the excavation of the four cross passage tunnels connecting the TBM bored Main Access Tunnel (MAT) and Emergency, Cable, Ventilation Tunnel (ECVT), and all associated works. Figure 2 below shows a general arrangement of the four tunnels. |
| | Main Roads Construction | 21 Sep 2020 | 05 Oct 2020 | 05 Oct 2020 |
| | |
| The Subcontractor is required to submit a fee proposal for the Main Roads Construction as below.
. Pipeline Rd -Adit Platforms Stage 2,
. Ravine Road Stage II (Ch. 0-7,000),
. Ravine Rd Stage II (Ch 7,000-14,000),
. Talbingo Spoil Rd,
. Talbingo Construction Access - Low Haul Rd,
. Talbingo Permanent Access, Talbingo Construction Access - Upper Haul Rd,
. Marica Trail Rd (Part I),
. Marica Trail Rd (Part II),
. Surge Shaft Access Rd,
. Marica West RD (Part I),
. Marica West Rd (Part II),
. Tantangara Rd, Quarry Trail Rd,
. Tantangara Barge Ramp,
. Tantangara Camp Rd (becomes Spoil Haul Rd),
. Tantangara Intake Access Rd (Upper),
. Tantangara Intake Access Rd (Lower) 1,
. Tantangara Stockpile Access Rd.
. Please see attached Drawings |
| | Construction of Water Treatment Plant | 01 Jul 2020 | 30 Jul 2020 | |
| | |
| The Subcontractor is required to submit a fee proposal for the design, fabrication and construction for water treatment plant for the main yard at Polo Flat in Cooma.
. Capacity 2Lts/sg with the following process equipment.
. Plug & Play type
. All internal piping and electrical cables included
. For batching plant and workshop operations as a containerised unit. |
| | Digital marketing and web services | 28 Apr 2020 | 13 May 2020 | |
| | |
| Future Generation is seeking to identify suppliers that have
the ability to provide:
-Digital marketing support
-Website design services
-Social media campaigns |
| | Earthmoving Drainage Stablisation and Pavement | 17 Apr 2020 | 01 May 2020 | |
| | |
| Future Generation is seeking to identify suppliers that have the ability and plant equipment and material to provide:
. Earthmoving, Drainage, Stablisation and Pavement at the Polo Flat Segment Factory
. Site preparation
. Wet and dry labour capability and supplies for civil works |
| | Fencing | 17 Apr 2020 | 01 May 2020 | |
| | |
| Future Generation is seeking to identify suppliers that have the ability, plant equipment and material to provide:
. Fencing services at the Polo Flat Segment Factory
. Labour and supplies for construction works
. Design of fencing requirements
. Supply of fencing items
. Supply of security items
. Installation of fencing |
| | Hydro mulching and Hydro Seeding | 01 Oct 2020 | 16 Oct 2020 | |
| | |
| The SOW for the hydro mulching contractor (Subcontractor) will be to provide personnel, equipment, and materials for hydro mulching and hydroseeding of slopes, batters, drains and any other areas as identified by FGJV. The SOW may include subsequent maintenance and watering of treated areas until such time that adequate cover and stability have been achieved to the satisfaction of FGJV. |
| | Main Camp Civil Works. | 25 Nov 2020 | 09 Dec 2020 | |
| | |
| Scope of Work includes:
. Site Establishment to carry out the works
. Location & Protection of Services if any.
. Topsoil Strip & Stockpile in the location indicated FGJV.
. Cut & Fil operation to construct the pad.
. Protection & Stabilization of Batter Slopes.
. Implementation of all Erosion Control Measures.
. Surface Drainage Excavation & Construction.
. Sub-Surface Drainage Excavation & Construction.
. Sediment Basin Excavation & Construction.
. Stormwater Drainage Excavation & Construction. |
| | Marica Camp Civil Works | 25 Nov 2020 | 09 Dec 2020 | |
| | |
| . Site Establishment to carry out the works
. Location & Protection of Services if any.
. Topsoil Strip & Stockpile in the location indicated FGJV.
. Cut & Fil operation to construct the pad.
. Protection & Stabilization of Batter Slopes.
. Implementation of all Erosion Control Measures.
. Surface Drainage Excavation & Construction.
. Sub-Surface Drainage Excavation & Construction.
. Sediment Basin Excavation & Construction.
. Stormwater Drainage Excavation & Construction. |
| | Pacific Hill Camp Civil Works | 25 Nov 2020 | 09 Dec 2020 | |
| | |
| . Site Establishment to carry out the works
. Location & Protection of Services if any.
. Topsoil Strip & Stockpile in the location indicated FGJV.
. Cut & Fil operation to construct the pad.
. Protection & Stabilization of Batter Slopes.
. Implementation of all Erosion Control Measures.
. Surface Drainage Excavation & Construction.
. Sub-Surface Drainage Excavation & Construction.
. Sediment Basin Excavation & Construction.
. Stormwater Drainage Excavation & Construction. |
| | Plant Equipment - Concrete | 03 Apr 2020 | 17 Apr 2020 | |
| | |
| Future Gen is interested in the following plant:
. Truck-mounted sprayed concrete boom pump.
. Concrete agitator truck 3.5m3/5m3/9m3.
. Concrete pump 30m3/87m3.
. Injection plant dosing system.
. Pneumatic concrete vibrator 75mm.
. Gasoline vibrating levelling screed 5250mm.
. Trowl.
. Electric concrete vibrator for cls 35mm.
. Jackhammer |
| | Plant Equipment - Valves and Sensors | 03 Apr 2020 | 17 Apr 2020 | |
| | |
| Future Gen is interested in the following plant:
. Pressure relief valves.
. Air release valves.
. Isolation valves.
. Gate valves.
. Water reservoirs.
. Flow valves.
. Water level sensors.
. Paddle level indicators.
. Flow dividers.
. Hydrant valves. |
| | Plant Equipment - Warehouse | 03 Apr 2020 | 17 Apr 2020 | |
| | |
| Future Gen is interested in the following plant:
. Bench grinder.
. Bench sander.
. Hydraulic press.
. Sliding bench saw.
. Hand tools.
. Industrial lathes.
. Magnetic drill press. |
| | Project Wide Spoil Managment | 05 Nov 2020 | 22 Nov 2020 | |
| | |
| The Subcontractor is required to submit a fee proposal for Project wide Spoil Management.
The project involves significant open and underground excavation which is expected to generate
about 8 million cubic metres of waste rock. Some of the spoil material will be re-used in the
construction of the permanent works, such as for road construction, back-filling of structures and
for tunnel portal accesses. However, most of the spoil material is to be placed in permanent spoil
emplacement areas within the project, at the locations listed
Within the following Areas:
Lobs Hole Main Yard
Lobs Hole GF01
Peninsula at Tantangara reservoir
Ravine Bay (wet and dry emplacement)
Rock Forest |
| | Road Works Design Upgrade -Package 3 | 01 Jul 2020 | 31 Jul 2020 | |
| | |
| The Subcontractor is required to submit a fee proposal for the design and approval of the road work for the critical points identified below. The following locations require road work upgrades. (See Appendix B for map locations):
1) Link Road & Lobs Hole Ravine Road South Intersection, Kosciuszko National Park.
2) Lobs Hole Ravine Road North & Snowy Mountain Highway Intersection, Kosciuszko National Park
3) Lobs Hole Ravine Road North, Kosciuszko National Park. |
| | Security Services Requirement- Lobs Hole/ Marica /Tantangara | 10 Jul 2020 | 11 Aug 2020 | |
| | |
| The Project site where security services are required defined as follows
Link Road Ravine Road Entrance
Snowy Mountains Highway Tantagara Entrance
Snowy Mountains Highway Marica Entrance |
| | Supply - Delivery - Installation - Testing and Commissioning of Gantry Cranes for Warehouses | 24 Nov 2020 | 09 Dec 2020 | |
| | |
| Scope of Work includes:
. Single girder overhead travelling cranes
. Length of runways
. 35 mtr - Capacity 10,000kg
. 24 mtr - Capacity 10,000kg
. 39 mtr - Capacity 5,000kg
. 24 mtr - Capacity 10,000kg
. 105 mtr - Capacity 20,000kg
. 35 mtr - Capacity 5,000kg
. Includes supply Installation Test and commissioning.
. All cables, conductor bars brackets and stoppers.
. Transport and delivery to site.
Prior to access to FGJV worksites all plant, vehicles and machinery must be clean and in good working order. |
| | Talbingo Adit - Adit Excavation D and B Slope Treatment Drainage. | 25 Nov 2020 | 22 Dec 2020 | |
| | |
| .- Excavation Adit and Service Area: Excavation and construction of Top Channels;
- All excavation to cover the: Adit Portal, Services Area, Settlement Pond and TBM Cradle (including necessary drill and blast activities);
- Slope treatments as detailed in TP01 including: Shotcrete System (Shotcrete, Steel Wire Mesh & Diagonal Strip Drain); Rockbolt & Subhorizontal Drainage;
- Tecco System (Erosion Control Matting & Tecco Steel Wire Mesh);
- Drainage channels on benches;
. Yard Surface Drainage excavation (AS AN OPTION)
. Yard Surface Drainage construction (AS AN OPTION).
. Settlement Pond construction (AS AN OPTION)
. Survey and setting out (AS AN OPTION)
. Fixed surveying points Installation
SoW S2-FGJV-TEC-SOW-TBC |
| | Tantangara and Quarry Trail Roads Construction | 27 Nov 2020 | 11 Dec 2020 | |
| | |
| . Site Establishment to carry out the works
. Road Construction |
| | Tantangara Camp Civil Works | 25 Nov 2020 | 09 Dec 2020 | |
| | |
| . Site Establishment to carry out the works
. Location & Protection of Services if any.
. Topsoil Strip & Stockpile in the location indicated FGJV.
. Cut & Fil operation to construct the pad.
. Protection & Stabilization of Batter Slopes.
. Implementation of all Erosion Control Measures.
. Surface Drainage Excavation & Construction.
. Sub-Surface Drainage Excavation & Construction.
. Sediment Basin Excavation & Construction.
. Stormwater Drainage Excavation & Construction. |
| | Tantangara Intake and Gate Shaft Earthworks Part 2 Excavation D and B Slope Treatment Drainage | 25 Nov 2020 | 09 Dec 2020 | |
| | |
| Scope of Work includes:
.- Excavation (Intake and Gate Shaft) and Service Areas
: - Excavation and construction of Top Channels;
- All excavation to cover the: intake and gate shaft, Services Areas, Settlement Pond (including necessary drill and blast activities);
- Slope treatments as detailed including: Shotcrete System (Shotcrete, Steel Wire Mesh & Diagonal Strip Drain); Rockbolt & Subhorizontal Drainage;
- Tecco System (Erosion Control Matting & Tecco Steel Wire Mesh);
- Drainage channels on benches;
. Yard Surface Drainage excavation (AS AN OPTION)
. Yard Surface Drainage construction (AS AN OPTION).
. Settlement Pond construction (AS AN OPTION)
. Survey and setting out (AS AN OPTION)
. Fixed surveying points Installation |
| | Utilities Trenching and Civils | 17 Apr 2020 | 01 May 2020 | |
| | |
| Future Generation is seeking to identify suppliers that have the ability and equipment to provide civil works to provide:
. Utilities, Trenching & Civils services at the Polo Flat Segment Factory
. Site preparation
. Underground and Infrastructure services
. Wet and dry labour capability and supplies for civil works |
| | Welding of TBM Components | 10 Jul 2020 | 10 Aug 2020 | |
| | |
| Future Gen wish to identify providers that have the ability to weld to assemble TBMs.
Subcontractor is to provide welding machines that are 450A and above, DC operated and can operate in both Electrode and MIG configurations.
Subcontractor is to ensure enough welding equipment is provided for the required quantity of welders and as below:
- Spare welding machine will also be required to cover breakdowns.
- Welding consumables, welding wire, welding electrodes and gas.
- The Contractor will also arrange required scaffolding and heating elements to ensure scope completion |