| | Transport and Installation | 19 Jan 2021 | 01 Feb 2021 | 01 Feb 2021 |
| | |
| The scope includes:
- Load out and transport of all equipment at agreed mobilization bases (likely Europe, Asia and Australia);
- Survey and installation preparations such as marine growth removal;
- Installation of up to five subsea structures (Max weight 140Te);
- Installation of up to 38km of electrohydraulic umbilical;
- Installation of up to 18km of flexible flowlines (max 10 ID);
- Installation of rigid tie-in spools, HFls and EFLs
- Stabilisation using mats and installation for crossings;
- Metrology and final spool configuration preparations;
- Riser pull-in activities on the Thylacine platform;
- Tie in and precommissioning of subsea equipment;
- As-built survey;
- System cold commissioning - OPTION
The Installation Contractor will be responsible for all installation engineering, design and manufacture of temporary works and installation aids and provision of all vessel and spread regulatory safety cases. Independent validation of all design, fabrication and installation activities will be performed in accordance with Australian Regulatory requirements by Company using a reputable international validation entity. |
| | Otway Offshore Project - Any Opportunities | 14 Jan 2019 | 28 Feb 2021 | 28 Feb 2021 | 
| | |
| Express interest for any opportunities that may arise for this project. |
| | Otway Offshore Project - Upcoming Potential Opportunities EOI | 28 Nov 2018 | 28 Feb 2019 | 28 Feb 2019 |
| | |
| Download the attached PDF listed under the 'Docs' column to review the potential work packages for the project. This is not an exhaustive list and additional work packages may be added. Submit your Expression of Interest to receive updates as specific work packages are listed. |
| | Provision of Structures - Spool Design - Fabrication and Testing Services | 02 Nov 2020 | 17 Nov 2020 | 17 Nov 2020 |
| | |
| The selected facilities consist of a flexible flowline system with sizes between 6inch and 10inch Internal Diameter.
This flowline system is complimented with rigid tie-in spools or flexible jumpers.
As part of this development, Beach have identified the need for subsea structures to tie-back these flexible flowlines. These may include:
- 6 Subsea tree tie-in rigid spools: 5 off
- 4-slot Subsea Central Manifold: 1 off
- Subsea Valve Manifold: 1 off
- Pipeline End Manifolds: 3 off
All equipment will consist of Corrosion Resistant Alloys for all production wetted parts. The spools will connect with Vertical Diverless Connectors.
The above Manifolds will all have ROV operable valves and Vertical and Horizontal Connectors to connect the Rigid spools and Flexible Flowlines. All Manifold will have foundations, either integrated or as a separate lift. Some of the manifolds may have instrumentation.
The Subsea Valve Manifold will contain a Beach provided Subsea Control Module complete with ancillaries.
Beach is seeking Expressions of Interest for potential bidders to provide the above equipment. The Equipment is to be provided as an integrated solution. The Scope of Work would therefore provisionally include:
1. Project Management
2. Safety Management
3. Quality Assurance and Quality Control
4. Procurement Services
5. Engineering
6. Detailed Design
7. Supply of components, including, but not limited to: Vertical Diverless Connectors, Horizontal Diverless Connectors, Diverless Connector Tooling, ROV operable valves, Hydraulically Operated valve(s), Wet Gas Flowmeters, CRA Piping materials, Anodes, Structure & Foundation materials.
8. Transport & Logistic services for all equipment
9. Fabrication, including coating of all equipment
10. Testing of all Equipment: Factory Acceptance testing of all components, Functional Testing, Hydrotesting/Leak testing, ROV Access simulation. |
| | Provision of Saturation Dive Support Services | 26 Oct 2020 | 28 Nov 2020 | 28 Nov 2020 |
| | |
| Beach have identified that Saturation Diving is necessary to tie-back the Phase 5 facilities, which will involve:
1. Installation and tie-in of a small subsea structure at the Platform base; and
2. Installation of a small subsea structure at a pre-installed Export pipeline Hot Tap location, including execution of the Hot Tap works and stabilisation of the Export pipeline (rock bolting).
Please see attached document for information on the scope of works.
Minimum Scope Requirements: Current Australian Vessel Safety Case for a hydrocarbon environment and a current Saturation Diving Safety Management System
Target Award Date: Early 2021 |
| | Subsea Metering System | 20 Nov 2020 | 03 Dec 2020 | 03 Dec 2020 |
| | |
| Beach are currently developing the Otway Phase 5 subsea facilities with a planned first gas date of Q1 2023. As part of the systems design the requirement for subsea metering has been identified to ensure the operability and integrity of the offshore production system and to provide production data for regulatory requirements and reservoir performance.
The scope requirement is to provide a minimum 3 off subsea metering systems that satisfy the primary functional requirements below:
- Measurement of Gas Flow Rate + 10% accuracy;
- Measurement of Formation Water Flow Rate;
- Detect the onset of formation water.
Additional items for consideration:
- Secondary functional requirement to measure condensate flow rate;
- Accuracy statements;
- Track record in Australia;
- Reliability;
- Technology Readiness Level;
- Retrievability (partial or full);
- Power requirements. |
| | Supply of Flexible Flowlines | 25 Nov 2020 | 01 Dec 2020 | 07 Dec 2020 |
| | |
| Beach are currently developing the Otway Phase 5 subsea facilities.
The selected facilities consist of a flexible flowline system suitable for hydrocarbon operations.
This flowline system is complimented with rigid tie-in spools or short flexible jumpers.
As part of this development, Beach have identified the need for subsea unbonded flexible pipe, to tie-back these subsea facilities. These may include:
- 10inch Internal Diameter Main Production line 3.9km
- 8inch Internal Diameter Infield Production line 4.0km
- 6inch Internal Diameter Infield Production line 1.4km
- 8inch Internal Diameter Infield Production Line 7.9km [Optional]
- 6inch Jumpers 50-100m (5 off) [Optional]
These flowlines are to be fully qualified, designed, manufactured and delivered in accordance with API 17J Specification for Unbonded Flexible Pipeline.
The products will need to be delivered complete with Midline connections (as needed), end-fittings, bend stiffeners/limiters and other ancillaries.
The product needs to be designed for water-depths up to 150m and will have operating temperature between approximately -25C (temporary) and 90C. In addition, it shall be suitable for a Maximum Operating pressure of up to 22MPag.
Beach is seeking Expressions of Interest for potential bidders to provide the above equipment. The Scope of Work would provisionally include:
1. Project Management
2. Safety Management
3. Quality Assurance and Quality Control
4. Procurement Services
5. Engineering
6. Detailed Design
7. Transport & Logistic services (up to delivery)
8. Fabrication/manufacturing
9. Testing of a/Manufacturing of all Equipment
10. Packing of equipment on Transport & Installation Reels
11. Load-out of equipment, either Incoterms 2020 FOB or FAS |
STATUS
|
|
B. WELLSITE OPPORTUNITIES ▲ CONTRACT
|
OPENS
|
FULL SCOPE CLOSES
|
PARTIAL SCOPE CLOSES
|
DOCS
|
FULL SCOPE EOI
|
PARTIAL SCOPE EOI
|
| | Casing accessories | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of casing accessories for onshore and offshore casing installations. Onshore wells are ERD with steps outs beyond 6km. |
| | Cementing services | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of downhole cementing equipment, materials and services for both onshore and offshore operations. Scope includes the provision of a bulk cement plant at Beach Energy's onshore supply base and development of cementing programs, cement blends suitable to the reservoir and wellbore properties and provision of technical expertise and equipment to perform the services. Equipment and services will be required to meet American Petroleum Institute standards. |
| | Drill fluid and fluid management services | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of drill fluid and fluid management equipment services. Scope will include a bulk fluid plant located at the Beach Energy onshore supply base, provision of technical advise for development of water based and sythenic based mud solutions for onshore ERD wells and offshore wells, and supply and management of drill fluid materials to meet the requirements of the project. Scope also includes all rig onshore and offshore fluid storage and treatment equipment and technical services. Equipment and services will be required to meet American Petroleum Institute standards. |
| | Fishing services | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of downhole drillstring fishing equipment and services for both onshore and offshore operations. Provision technical fishing expertise for a variety of downhole tooling. |
| | Offshore cement head/liner hanger cement head rental services | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of cement head / liner hanger cement head rental and technical services for offshore operations. Equipment and services will be required to meet American Petroleum Institute standards. |
| | Otway onshore offshore DD/MWD/LWD | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of DD/MWD/LWD services for both onshore and offshore operations. Provisions of all personnel, tools and technical support required. Hole sections will vary from 26" to 8 1/2" with rotary steerable required for sections 17 1/2" and below. Onshore wells are ERD with steps outs beyond 6km. Equipment and services will be required to meet American Petroleum Institute standards. |
| | Otway onshore offshore mudlogging | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of mudlogging equipment and services for both onshore and offshore operations. Provision of all personnel, testing equipment and laboratory support as required. Equipment and services will be required to meet American Petroleum Institute standards. |
| | Otway onshore offshore Tubular Conveyed Perforations (TCP) | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of well testing and TCP equipment and services for both onshore and offshore operations. Equipment and services will be required to meet American Petroleum Institute standards, as well as compliance with Australian explosives regulations. |
| | Wireline logging and tractor services | 18 Dec 2018 | 11 Jan 2019 | 11 Jan 2019 | 
| | |
| Provision of wireline equipment and services for both onshore and offshore operations. Both onshore and offshore operations will include tractor services. Onshore wells are ERD with steps outs beyond 6km. Equipment and services will be required to meet American Petroleum Institute standards. |
| | Otway Gas Plant - Well Clean-Up Skid | 17 Jul 2019 | 31 Jul 2019 | 31 Jul 2019 | 
| | |
| Design and construction of a cyclonic solids recovery unit installed at the Otway Gas Plant, in the outlet from one of the Slugcatcher Liquids Receivers to filter residual solid material from drilling being transported from the wellbores to the Otway Gas Plant.
The new unit will be installed in a two-stage operation, with the first stage being to install the tie-in points and valving (to be designed) into the process pipework during the February/March 2020 Otway system shutdown. This will enable the clean-up skid to be installed (and subsequently removed) with the Otway Gas Plant online, and without any compromise to production.
The clean-up skid itself will be integrated into a single transportable unit. The active elements of the skid will be scalable to adapt to variations in flowrates, and even to installation in other Beach Energy facilities in the future. |
| | Otway Offshore Subsea Wet Gas Flow Meter Supply | 16 Jul 2019 | 31 Jul 2019 | 31 Jul 2019 | 
| | |
| Provision of 2 off subsea wet gas flow meters as a fully engineered package to operate as part of a complete subsea tieback system. Suppliers scope includes project management, engineering and analysis, supply of two (2) subsea wet gas flow meters, supply of ancilliary items (wet gas meter similator console, engineering and diagnostic console software), packaging of supplied equipment, all inspection, testing (including hydrostatic and hyperbaric), 3rd party verification, documentation, supply of field service engineers for setup and pre-commissioning activities. Equipment and services will be required to meet the relevant API and ISO codes and standards. |
| | Otway Offshore Project - Phase 4 - Subsea Installation Works | 26 Aug 2019 | 09 Sep 2019 | 09 Sep 2019 | 
| | |
| The scope of work comprises:
- project management,
- installation engineering,
- procurement /fabrication of installation aids,
- procurement of permanent works duplex piping and bends,
- fabrication and installation of two permanent subsea duplex spools,
- recovery of an existing subsea spool,
- installation of electrical flying leads/ electro-hydraulic flying leads,
- subsea ROV and precommissioning operations.
An offshore dynamically positioned installation vessel will be mandatory to perform the work and shall have a current Australian Offshore Petroleum Safety Legislation, NOPSEMA approved Vessel Safety Case, complete with:
- a minimum 70 t active heave compensated crane,
- two-off work class ROVs.
The offshore campaign is planned for Q4 2020 approximately 70 km offshore Victoria in 85m water depth. |